Automotive Careers Training Center Project Sources and Budget
Project Budget
| Construction | $16,886,034.00 |
| Utilities | $257,400.00 |
| Site Work | $790,874.00 |
| Construction Contingency | $537,129.00 |
| Furniture, Signage & Movable Furniture | $1,750,320.00 |
| Special & Technical Equipment | $406,692.00 |
| Architectural & Professional Services | $1,495,907.00 |
| Insurance, Soil, Permits, Relocation Costs | $180,180.00 |
| Scholarship & Program Endowment | $500,000.00 |
| Fundraising Costs | $60,800.00 |
| Uncollectible Pledge | $105,000.00 |
Total Budget $22,940,336.00
Sources
| Federal ARPA | $4,700,000.00 |
| College Funds | $14,740,336.00 |
| Fundraising | $3,500,000.00 |